Kat’s Status Report 2/7

This week the team worked on the project proposal, I worked on the gaant chart and software requirements slides. We have not ordered our parts yet, however we have a good idea of the parts we need to order and will do soon at the beginning of next week. I specifically want to work on research of the machine learning datasets and classifying data of 3-dimension signaling. I also want to practice with some parts from inventory for the hardware to software communication.

Teadora’s Report for 2/7/2026

This week I contributed to the project proposal, specifically the slides explaining hardware. I also did the website setup. I think we are slightly behind schedule since we haven’t ordered parts yet. We will resolve this by ordering parts online and from the inventory in our Monday meeting. I want to work on board to computer console communication this week since we can get a RPi from inventory and play around with it while waiting for flex sensors.