Team Status Report for 3/15

From the feedback received for our design report, our current risks are to figure out the cloud implementation in more detail and have something we can use to integrate with the Edge compute part. Additionally, we need to test the camera to see if it matches what we need as soon as possible. To that end, we have gotten a barebones and minimal but still usable cloud implementation for our case, and Tzen-Chuen will be hooking up the camera in the next couple days.

Currently, there are no changes to the existing design. We forecast changes next week however, as the major components should be integrated and we will begin testing our MVP, likely learning what could be improved. The current schedule is MVP testing next week, with working on new/replacement components/making the requisite changes the week after that. 

Right now, we have the locally run code mostly finished, and it can be found here. We also have made large strides on the cloud side of things, with databases set up.

Leave a Reply

Your email address will not be published. Required fields are marked *