Luke Han Status Report 3/8/2025

Over the past two weeks, I have primarily worked on the camera and projector system as well as refined the design report. Before the break, I dedicated significant time to the design report, particularly working on the design requirements, design trade studies, and risk mitigation plans. Additionally, I contributed to the project budget, ensuring our resource allocation aligns with project constraints.

I conducted preliminary tests to the camera and projector to assess their capabilities. This included evaluating calibration accuracy, image capture quality, and potential integration challenges. However, our progress is currently hindered because our group has yet to receive the pool table, which was scheduled for delivery two weeks ago. As a result, I am not on track, and our timeline may be impacted until we can begin full system integration.