Risks and Contingency Plans
The most significant risk right now is that our model evaluation is behind schedule, which may delay integration with the IR wand system. Since we need to compare CNN, RNN, and LSFM models before finalizing one for deployment, delays in testing could impact our further implementation and optimization.
To mitigate this risk, Olina will prioritize completing model evaluations next week and continue working during spring break weekend to ensure we stay on track.
Design Changes
No changes to our design at this point.
Schedule
We are behind schedule due to delays in model testing. However, we are working to catch up next week and will use spring break to ensure we meet our project milestones.