Howard Ma’s Weekly Status Report for 2/22/25

Personal Accomplishments

  • Completed tubing size analysis and ordered updated parts to ensure proper fit and functionality within the system for optimizing fluid flow and maintaining system efficiency.
  • Researched circuit connections and pinout configurations for integrating solenoid valves and robotic arms, preparing for embedded system control once the new components arrive.
  • Assembled the robotic arm to prepare for preliminary testing for full system integration later on.

Next Week Deliverables

  • Develop a working physical prototype to evaluate the feasibility of the system and identify and refine any potential adjustments.
  • Complete the design review report
  • Produce a circuit layout for embedded integration

Status Report: On Schedule