This past week, I was catching up on a lot of work since I was really sick the previous week and also had a midterm on Thursday. Despite that, I made significant progress on the project. I worked on the design presentation slides and presented them on Monday. Additionally, I have been working on OpenCV gesture recognition, ensuring it runs locally on my computer. The setup is now complete, and I am currently in the process of testing the accuracy of the model. Now that I have the gesture recognition working locally, the project is back on schedule. The progress aligns with our timeline, and I am ready to move forward with the next steps.
For the upcoming week, I plan to
- Continue testing the accuracy of the gesture recognition model
- Work on Figma design for the website interface.
- Start working on the networking portion of the project for the webapp
- Begin drafting and finalizing the design review report submission.