Jun Wei’s Status Report for Feb 23 2025

1. Personal accomplishments for the week

1.1 Design report

For this week, most of my efforts were concentrated on producing the design report that was due on Feb 28. The use case and its associated requirements were formally presented in the form of an IEEE-style article. Doing the report also allowed me to formally derive numerical specifications relating to the camera system, specifically the minimum FOV required for our use case.

2. Progress status

I am currently on schedule and have completed the tasks set out for the week, apart from developing the data transmission pipeline from the camera to the RPi.

3. Goals for the upcoming week

  • Developing camera data transmission pipeline and lighting control
  • Testing image stitching (if the camera new arrives in time) / Begin construction of motorized camera slider (if the slider arrives in time)