MM Demangone’s Status Report for 2/15/2025

For this week, I had revised the components that we need for our design. I had drawn out several block diagrams and iterations of our design as we were optimizing our hardware. I have completed the medication Django form and model to be used in our web app and have pushed it to our GitHub. I also worked on the design presentation, namely the block diagram, solution approach, software implementation, hardware implementation, testing, and verification. Additionally, I will be presenting the design presentation in class on Monday, so I have spent time preparing for that presentation as well. I am on track with the schedule that we had set! Next week, I will complete MySQL database creation to store the users’ medications. Additionally, I will start writing some code for the RaspberryPi, so once it arrives, we will be ready to start testing and vetting the code. Lastly, I will work on the Design Proposal document with the rest of my team.

Final Design

High-level Block Diagram

Leave a Reply

Your email address will not be published. Required fields are marked *