Team Status Report for 02/24/2024

This week was a productive week for our team. We finished the design presentation proposal together and will look into feedback and incorporate them! Right now, we are trying to order the Jetson and also get parts from our 18500 kit! We are also waiting for access to  ImageNet database, which is out of our control right now. We hope that this turns out smoothly, as if not, we will have to wait longer for the parts to arrive and access to be given in order to test things out. While we wait, we plan on making the most out of our time by working on tasks that we do not have to wait on materials or access for.

 

We have no design or schedule changes right now.