Sruti’s Status Report 04/29

Progress:

  • Updated audio cues
  • Created a demo video that shows functionality of the mirror
  • Worked on optimization of the software. There was a large amount of lag and wait time between each pose previously. I optimized the code so that the camera frames would be processed faster and each video capture would not start and end between each pose.
  • Worked on the final report and presentation.

Overall, I think we are all set and on track for the demo!

Remaining steps:

  • We are meeting the yoga instructor this week to get the remaining testing metrics
  • Complete final deliverables like report, poster and video