Jeff’s Status report for 4/29

Personal Progress

This week I finished building the frame for the final demo and lights.
We also tested the setup to make sure it works. I also performed full comprehensive on the hardware system to make sure it’s still performing normally.

Plans for Next Week

We plan on fine tuning the demo setup and also working on the final poster and documentations.

Team Status Report for 4/22

Risk and Risk Management

The biggest risk to our project right now is not finishing the final document. Our mitigation plan is to start early.

System Design Changes

As of now there hasn’t been a change to the existing design of the system.

Schedule

The schedule has not changed and everyone is on schedule.

Jeff’s Status report for 4/22

Personal Progress

This week we did extensive testing and confirmed that our blinds works. There is however some amount of error at the edges and the blinds work much slower and less consistent when adjusting the blinds upwards. This is because it requires much more torque to make the blind goes upwards and the gear occassionally skips and had to go much slower to get the torque.

I also designed and built the frame for the final demo. I also worked on the final presentation slides.

We are on schedule and nothing needs to be changed.

Plans for Next Week

We plan on finishing the final document and finish building frame.

Jeff’s Status Report for 4/8

Personal Progress

This week I updated the hardware software interface to allow for interruption of blinds. I also got cardboard to build the fake window frame for the final demo and began construction of the frame.

I am currently on schedule personally since the hardware system is fully complete and am waiting to the software team to be fully finished to perform full system testing.

Plans for Next Week

There plenty of sunny days on the coming week so we will be doing full integrated system testing and calibration. I will also finish building the frame.

The tests planned for the hardware system include sending in test vectors asking the blinds to move the blinds at every 10 cm intervals (10cm, 20cm, 30cm from the top). I also plan to test the light detect circuit by moving it into the light and not light and make sure the response is correct.

Jeff’s Status Report for 4/1

Personal Progress

This week I was able not able to fully assemble the blinds because I can’t install the blinds into my bedroom due to my lease and tried to find solutions. I’ve considered plywood, pvc pipes, cardboard, and other ways to build a frame but because I’m not allowed into the woodwork area and lack of power tools, we settled with command strips. After placing the order for the command strips, I manually held up the blinds to test if it will work and what is the rate the blinds can move. I also helped Dianne and Elizabeth in software testing and integration.

I am current still behind on schedule because of the issue detailed above. There is no real way to adjust the schedule since the arrival of the command strip is outside our control and can only shorten testing period.

Plans for Next Week

If the command strips arrive by next week, I will begin full integrated testing in real environment. In the meantime I will help test software accuracy and think of other temporary measures to enable earlier full system testing.

Team Status Report for 3/25

Risk and Risk Management

The major risk that we have is related to full integration testing. Since real time testing requires the weather to be sunny and we also have other time commitments so we need the sunny day to line up with our availability to test for capstone. This makes rapid revision and testing very difficult. We aim to mitigate this by utilizing past data from sunny day to simulate a sunny day. We won’t be able to get real life confirmation but we can double check the response to what we think is the ideal response.

System Design Changes

As of now there hasn’t been a change to the existing design of the system.

Schedule

The schedule has not changed yet, and everyone is roughly on track for the time being.

Jeff’s Status Report for 3/25

Personal Progress

This week I was able to speed up the motor system to a reasonable speed by  setting the Vref to the correct voltage and to send out control pulses at the fastest pace possible. I also finish setting up the interface for the software people to send the control they want the motor to perform. I also finished assembling the 3D printed gear pieces with the motor.

I am current still on schedule and no need for adjustment.

Plans for Next Week

To test the motor system with actual blinds attached.

Jeff’s Status Report for 3/18

Personal Progress

This week I was able to test our light detection circuit in actual sunlight and was able to extract the threshold for sunlight as shown below in figure 1. I was also able to get the stepper motor working. It can rotate in both direction and at different speeds and duration.  I also set up the initial serial interface to receive some basic commands from the serial monitor (currently just adjusting the direction of the rotation.  I also learned how to use Cura for 3D printing slicing for the 3D printing request for the gear to turn the blind. I submitted a request for a quote to make sure it fits in our budget as shown in figure 2.

figure 1: Left is direct sunlight, Right is ambient light

I am current still on schedule and no need for adjustment.

 

Plans for Next Week

The motor currently turns very slowly and I’ve been researching how to make it turn faster. I found a few solutions and plan on implementing them and testing it next week. I also hope the gear gets printed by next week so I can attach it to the motor and begin testing on the actual blinds.

Jeff’s Status Report for 3/4

Personal Progress

This week our team just focused on writing our design document. I focused on writing all the subsections that involves the sensor system and motor system.  I also worked on writing the related work section and risk mitigation plan section.

We are on schedule and don’t need to make any changes to my schedule and plan.

Plans for Next Week

I plan to test the light detection circuit under actual sunlight so I can find the brightness threshold for actual sunlight. I also hope to get the motor control fully completed.

Team Status Report for 2/25

Risks and Risk Management

The most significant risk as of now is probably waiting for the Intel RealSense D455’s arrival because we really need to the D455 to meet our project requirements. It is the prerequisite for a lot of the parts for our project, like the face detection software testing. This risk is being managed by working with the L515 we currently possess since the data produced by the D455 and L515 should be very similar outside of range and resolution differences (which is why we haven’t returned it yet). They use the same library (pyrealsense2) as well.

System Design Changes

There are no system design changes this week.

Schedule

The schedule only changed for Jeff, who is handling hardware, since the D455 did not arrive this week. Because of this, Jeff has moved the task of building the motorized blinds up the schedule until the D455 camera arrives, and has been working on that this week. The schedule for the software side of things has not been changed because the LAOE algorithm does not need camera data, and the face detection software is temporarily being made with the L515 camera data.

Teamwork Adjustments

No adjustments have been made as of now, as everyone is roughly still on schedule. All team members have been meeting up with each other throughout the week, and there are no new design challenges yet.