What are the most significant risks that could jeopardize the success of the project? How are these risks being managed? What contingency plans are ready?
The key risks for our project at this point in time are primarily related to integration. In particular, as we are behind with the development of the mobile application, we are concerned about having enough time to fully flesh out and test the iOS Bluetooth Code. Additionally we have had some delays in the production of our PCB board, so we are concerned about having enough time to test everything works.
Were any changes made to the existing design of the system (requirements, block diagram, system spec, etc)? Why was this change necessary, what costs does the change incur, and how will these costs be mitigated going forward? Provide an updated schedule if changes have occurred.
We have made some simplifications to our overall design by removing some of the more complicated features for pattern design and editing, to focus on getting our subsystems integrated