Team Status Report for April 1

What are the most significant risks that could jeopardize the success of the project? How are these risks being managed? What contingency plans are ready?

As we are slightly behind schedule in terms of both the hardware and mobile application development, currently our primary concerning is having enough time for testing and integration.

Were any changes made to the existing design of the system (requirements, block diagram, system spec, etc)? Why was this change necessary, what costs does the change incur, and how will these costs be mitigated going forward? Provide an updated schedule if changes have occurred.

We have not made any major changes to our schedule or our design system this week.

Please enumerate how you have adjusted your team work assignments to fill in gaps related to either new design challenges or team shortfalls.

Although we mentioned having issues with our Hardware design and PCB development in our last status report, we were able to make a breakthrough this week. Particularly we were able to meet with a Professor to work through a draft of our PCB board to fast-track manufacturing a prototype, and we able to successfully program our STMWB to communicate wth an iOS device via BLE. We are hoping this will reduce the time required for firmware development and allow Saniya to swap back over to assisting with iOS development