Team Status Report for 04/22

Due to the delays we experienced with the parts we ordered, our biggest risk is being able to test our parts and ensure we don’t need to pivot or order any new parts. Also, because of a delay in our PCBs, we have been set back a little. We hope to finish the fabrication of all the PCBs this weekend, as we currently have 3 rows fabricated.

We made a change in our design from using batteries to instead being plugged into a wall outlet, as this would reduce costs, and also make our system more compact. Apart from this, we have not changed any of our original plans until MVP.

Our schedule has not changed significantly, even though we had delays with our parts, as we were able to catch up on some work during the week of carnival to account for any delays in the following weeks.