Team Status Report for 2/19

Currently, our team is pushing to complete our mechanical and CV pipeline as soon as possible, as per Professor Kim’s recommendation. We are approximately on schedule, although it’s likely before we finalize our slides this weekend we may add more detail to our schedule to break down the tasks more. We completely redid our block diagram and went into more detail with specifying the system, CV, and hardware components. We also put in orders for both the projector and central motor, so we can begin putting together the product as soon as possible. While we wait for the hardware, we can work on our design report and code design for each area.