Rama’s Status Report for 3/26

In the beginning of the week, I simplified the circuit and found mini breadboards to use in the final assembly of the projector stand. I wrote movement functions needed for calibration and wrote a draft of the functions needed to move the projection given the information collected over CV. I attended the National Society of Black Engineers (NSBE) Conference in Anaheim that started on Wednesday and I will be back Sunday night so I was not able to make further progress than this. On Monday, I hope to make the last order for parts and test out the draft functions. My goal by the end of the week is to have the physical system assembled so it can be properly tested with my team member’s work and code.