What did you personally accomplish this week on the project?
Worked on integrating all parts of the parking management software system;
Worked on making a presentation video for the interim demo, and presented video to Professor Kim and TA Manny at demo;
Also worked on helping XuKe with his OpenCV part to speed up his progress.
Is your progress on schedule or behind?
My progress is behind due to
- Still blocked on XuKe’s OpenCV plate visual recognition development. There is a very high rate of inaccuracy, which will hinder the success and function of our system;
- I am facing some issues with raspberry Pis sustaining unstable connection with the server. I am trying to rectify the issue as quickly as possible.
What deliverables do you hope to complete in the next week?
I am planning to work on enhancing the navigation system next week and help XuKe and Grace with their critical parts (openCV and LED strip controls);