Txanton’s Status Report for 05/01/2021

This week we had the discussion with the Eberly center which I felt was pretty productive. We were able to give some feedback which seemed to be well received and we were also able to hear some of the experiences of the other teams.

Regarding the project, this week I helped to interface the overlay code with the beamforming code by receiving the data over UDP.  I also helped to tweak some of the specific values as we were testing in order to make the overlay code better correspond with the constraints of our system. Luckily from our testing it seems to be corresponding with the location of the transmitting device pretty well so I am hopeful that we won’t need to make any significant changes for the final video.

Next week I will continue to help the team test the accuracy and make any future adjustments as we prepare for our final video and report.