Currently, the most significant risk to the success of our project is that we are already behind schedule (based on our Gantt chart). We wanted to have our board by this coming Monday, but we haven’t ordered a board yet because we are potentially changing our first choice board from the Xavier NX to the Xavier AGX. This is because the AGX is available according to the inventory list, so it’s now within our budget. The only thing that is preventing us from finalizing our decision is that we haven’t been able to find as many resources for using OpenPose on the AGX as we have been able to find for using OpenPose on the NX.
We’re planning on finalizing which board we want to use by Sunday so we will still have time to get an NX approved by our TA and ordered by Tuesday. If we end up choosing to use an AGX, we won’t be very behind schedule because we could pick that board up on Monday.