Abha’s Status Report for Feb 15

Abha’s Status Report for Feb 15

This week, I first worked on finalizing the Bill of Materials. I specc’d out the exact parts for the Text Display, Face Display, Motors, and the Motor Driver. The Text Display will be a 5in x 3in LCD screen, which connects to the Raspi through HDMI 

Jade’s Status Update for Feb 15

Jade’s Status Update for Feb 15

This week I worked on finding the components I need for the audio input, as well as choosing a speech recognition package and investigating text to speech packages. For audio input hardware I decided to go with a simple TRS to USB soundcard input into 

Ashika’s Status Update for Feb 15

Ashika’s Status Update for Feb 15

This week, I accomplished three main tasks. First, I found a story dataset for the templates: a collection of 177 of Aesop’s Fables. All these stories are about 5-7 sentences long, so they fit our desired template length and will be the only story dataset 

Team Status Update for Feb 15

Team Status Update for Feb 15

The dimensions of KATbot are as shown above. Risks and Risk Management: The most significant risk is a poor fill in the blank algorithm for the machine learning based stories. Without this feature, the stories will not be cohesive or grammatically correct, defeating the purpose