Abby’s Status Report for Oct 25

This week, I focused on finding the correct servo motors to order to begin construction of our embosser. I sent in an order form for these. I completed the two readings, video, and the ethics assignment. I continued to work on the CAD of our design, having it complete is a deliverable I plan to have at the end of next week. Our progress is a little behind, but there is slack room in our schedule so we can continue work as normal. I additionally hope to have some 3D prints completed.