This week my work consisted of working on the Design Report. My contributions were the “Design Trade Studies”, “System Implementation”, and “Project Management” sections.
My work isn’t necessarily behind, but I’m concerned that we might not be able to begin integration this week, which is our goal. The main reasons are possible delays in part arrivals and ongoing correspondence with the Office of Disabilities.
Next week I hope to build embossing head and frame prototype, as well as, purchase a battery pack and charging board to integrate with our microprocessor.