At the beginning of the week, I focused on the project website. I worked on setting it up and started developing the upload functionality so that files can be submitted through the site. I got the upload feature to work so it should be ready to connect to the Raspberry Pi once testing for image to vectors begins.
I will be presenting for the team on Monday, so later in the week, I shifted towards preparing for our upcoming presentation. I worked on refining the slides and practicing my talking points. I also reviewed the overall presentation to make sure it flows smoothly.
I am currently on schedule with my tasks. Next week, I plan to test the upload feature with the Raspberry Pi and continue expanding the website with project content. I also plan to incorporate feedback from the presentation into our design work. When the motors arrive, I plan on also helping out with the integration.