Team A3: SNIFF – Massively Mobile Air Quality Sensors
  • Introduction and Project Summary
  • Weekly Status Reports
  • Proposal
  • Design Review
  • Final Project Documents

jjalacce

Team Status Reports

Team’s Status Report for December 6, 2025

Note: Our team has compressed our images, but the image upload quota is still full, so this report does not have photos that we would have liked to attach. Presently our most significant risk is a mounting failure destroying our Visor making it so that we cannot show it off Read more…

By jjalacce, 2 weeks ago
Uncategorized

John’s Status Report for December 6, 2025

Note: Our team has compressed our images, but the image upload quota is still full, so this report does not have photos that we would have liked to attach. Before thanksgiving break, we did some on the bike testing focusing on data collection and full system tests and taking photos Read more…

By jjalacce, 2 weeks ago
Team Status Reports

Team’s Status Report for November 22, 2025

Note: Our team has compressed our images, but the image upload quota is still full, so this report does not have photos that we would have liked to attach. Risks One risk is that our mounting system fails causing a bicycle crash and destroying the Visor. This is being mitigated Read more…

By jjalacce, 3 weeks ago
John's Status Reports

John’s Status Report for November 22, 2025

Note: Our team has compressed our images, but the image upload quota is still full, so this report does not have photos and videos that we would have liked to attach. This week I helped with manufacturing our MVP prototype visor which involved a large amount of sanding and glueing. Read more…

By jjalacce, 4 weeks4 weeks ago
John's Status Reports

John’s Status Report for November 15, 2025

This week I have finished wiring up all of the Visor Components. I have also integrated batteries into both the Visor and the Station systems. Another big focus this week was preparing for and performing the interim demos. Regarding Verification and Validation: We have verified that the data packets generated Read more…

By jjalacce, 1 month ago
Team Status Reports

Team’s Status Report for November 8, 2025

A possible risk is that we are too late in the construction of the Visor that testing is pushed back. This could happen due to delays piling up in various parts of the project progression and pushing back our schedule. To manage this risk, we have been working on other Read more…

By jjalacce, 1 month1 month ago
John's Status Reports

John’s Status Report for November 8, 2025

This week I preformed some data collection integration tests where I sat outside of Hammerschlag Hall collecting data and ensuring that all of the formatting requirements for further down the pipeline are being meet along with ensuring that our data collection script doesn’t have any other issues. Building on the Read more…

By jjalacce, 1 month1 month ago
Uncategorized

Team’s Status Report for November 1, 2025

A possible risk is that we are too late in the construction of the Visor that testing is pushed back. This could happen due to delays piling up in various parts of the project progression and pushing back our schedule. To manage this risk, we have been working on other Read more…

By jjalacce, 2 months ago
John's Status Reports

John’s Status Report for November 1, 2025

This week I was able to read from all of our sensors when they were integrated all together. While system compatibility was paramount when selecting components to see all of the sensors having no communication conflicts, library issues, or other problems when integrated together is a relief. Once these integration Read more…

By jjalacce, 2 months ago
Team Status Reports

Team Status Report for October 25, 2025

A possible risk is that we are too late in the construction of the Visor that testing is pushed back. This could happen due to delays piling up in various parts of the project progression and pushing back our schedule. To manage this risk, we have been working on other Read more…

By jjalacce, 2 months ago

Posts navigation

1 2 Next
Recent Posts
  • Jaehyun’s Status Report for December 6, 2025
  • Team’s Status Report for December 6, 2025
  • Stella’s Status Report for December 6, 2025
  • John’s Status Report for December 6, 2025
  • Team’s Status Report for November 22, 2025
Archives
  • December 2025
  • November 2025
  • October 2025
  • September 2025
Categories
  • Jaehyun's Status Reports
  • John's Status Reports
  • Stella's Status Reports
  • Team Status Reports
  • Uncategorized
Meta
  • Log in
  • Entries RSS
  • Comments RSS
  • WordPress.org
  • Design Review
  • Final Project Documents
  • Introduction and Project Summary
  • Proposal
  • Weekly Status Reports
Hestia | Developed by ThemeIsle