Team’s Status Report for November 22, 2025

Note: Our team has compressed our images, but the image upload quota is still full, so this report does not have photos that we would have liked to attach. Risks One risk is that our mounting system fails causing a bicycle crash and destroying the Visor. This is being mitigated Read more…

By jjalacce, 3 weeks ago
Stella's Status Reports

Stella’s Status Report for November 22, 2025

Note: Our team has compressed our images and videos, but the media upload quota is still full, so this report does not have photos that we would have liked to attach. This week, our group finished out MVP prototype manufacture for the SNIFF Visor. We put together the different parts Read more…

By stellai, 4 weeks ago
John's Status Reports

John’s Status Report for November 22, 2025

Note: Our team has compressed our images, but the image upload quota is still full, so this report does not have photos and videos that we would have liked to attach. This week I helped with manufacturing our MVP prototype visor which involved a large amount of sanding and glueing. Read more…

By jjalacce, 4 weeks4 weeks ago
Jaehyun's Status Reports

Jaehyun’s Status Report for November 22, 2025

Last week, I helped with physical build of the Visor, helped set up the LTE board, and hosted the SNIFF website on a DigitalOcean droplet so that it is not locally hosted anymore: https://subcarinate-eartha-uncompulsive.ngrok-free.dev/. Soon, we will own the domain, sniffpittsburgh.com. For the Visor, I helped sand the components, remove the Read more…

By jaehyun3, 4 weeks4 weeks ago
Stella's Status Reports

Stella’s Status Report for November 15, 2025

Note: Our team has compressed our images, but the image upload quota is still full, so this report does not have photos that we would have liked to attach. This week, I made adjustments to the servo mounting, and added in holes to accomodate the heatset inserts to the lid Read more…

By stellai, 1 month ago
John's Status Reports

John’s Status Report for November 15, 2025

This week I have finished wiring up all of the Visor Components. I have also integrated batteries into both the Visor and the Station systems. Another big focus this week was preparing for and performing the interim demos. Regarding Verification and Validation: We have verified that the data packets generated Read more…

By jjalacce, 1 month ago
Team Status Reports

Team Status Report for November 15, 2025

Note: Our team has compressed our images, but the image upload quota is still full, so this report does not have photos that we would have liked to attach. Risks The heat set inserts may not come in on time. To mitigate this, we will use the larger inserts and Read more…

By jaehyun3, 1 month1 month ago
Jaehyun's Status Reports

Jaehyun’s Status Report for November 15, 2025

Last week, I made little progress because of the Interim Demo. I worked on creating a testing framework for the website using Locust, a python-based load generator. With Locust, I can vary the number of users and control RPS (Requests per second), which allows me to test for the saturation Read more…

By jaehyun3, 1 month1 month ago
Jaehyun's Status Reports

Jaehyun’s Status Report for November 8, 2025

Last week, I made major progress on the website and Adafruit Feather code. The website has had a design overhaul to make it easier on the eyes. First, I got rid of the large navbar at the top because it was overlapping over the air quality popups and overall reducing Read more…

By jaehyun3, 1 month ago
Stella's Status Reports

Stella’s Status Report for November 8, 2025

This week, I adjusted the inserts of the main Visor body to fit the basket more flush. I also condensed the sensor cavity because the top opening just needed to accomodate the mounted sensors.   Because the sensor cavity combined with the main body was too big for the printer Read more…

By stellai, 1 month ago

Posts navigation

1 2 Next
Recent Posts
  • Jaehyun’s Status Report for December 6, 2025
  • Team’s Status Report for December 6, 2025
  • Stella’s Status Report for December 6, 2025
  • John’s Status Report for December 6, 2025
  • Team’s Status Report for November 22, 2025
Archives
  • December 2025
  • November 2025
  • October 2025
  • September 2025
Categories
  • Jaehyun's Status Reports
  • John's Status Reports
  • Stella's Status Reports
  • Team Status Reports
  • Uncategorized
Meta
  • Log in
  • Entries RSS
  • Comments RSS
  • WordPress.org
  • Design Review
  • Final Project Documents
  • Introduction and Project Summary
  • Proposal
  • Weekly Status Reports
Hestia | Developed by ThemeIsle