Team Status Reports

Team’s Status Report for September 27, 2025

The most present risk to derailing our team’s progress is getting our parts delivered in a timely manner. While currently this does not seem to be affecting the team’s schedule, the current mitigation is to focus our weekly effort on parts of the project that don’t require any physical components Read more…

By jjalacce, 4 weeks ago
Jaehyun's Status Reports

Jaehyun’s Status Report for September 27, 2025

What did you personally accomplish this week on the project? Give files or photos that demonstrate your progress. Prove to the reader that you put sufficient effort into the project over the course of the week (12+ hours). This week, I spent almost all of my time working on the Read more…

By jaehyun3, 4 weeks4 weeks ago
Stella's Status Reports

Stella’s Status Report for September 27, 2025

This week, I helped with working with the API for the ACHD database of air quality measurements. In addition to this, the team and I continued to refine and nail down our design requirements for Jaehyun’s presentation next week, which will be important for our project trajectory. I also started working Read more…

By stellai, 4 weeks4 weeks ago
John's Status Reports

John’s Status Report for September 27, 2025

This week I have ordered all of the parts on our planned budget so far. This should allow us to create a working Sniff visor and Sniff Station. Additionally, I have setup meetings for next week with both a member of the BU team that completed a similar capstone project Read more…

By jjalacce, 4 weeks4 weeks ago
Stella's Status Reports

Stella’s Status Report for September 20, 2025

This week, Jaehyun, John, and I continued to refine our parts list. We specifically focused on our planned LoRa network, researching how to use LoRaWAN and LoRa, as well as looking into how we wanted to put together our LTE board setup. For the cellular network we are planning to Read more…

By stellai, 1 month1 month ago
Team Status Reports

Team Status Report for September 20, 2025

What are the most significant risks that could jeopardize the success of the project? How are these risks being managed? What contingency plans are ready? The most present risk to derailing our team’s progress is ordering our parts and getting them delivered in a timely manner. While currently this does not Read more…

By jjalacce, 1 month1 month ago
John's Status Reports

John’s Status Report for September 20, 2025

This week I accomplished with my team, selecting the parts for the LoRa network that will be facilitating communication between the sensor box on the bike and the box located at the station. We also have selected a cellular board and service provider that we believe will work for our Read more…

By jjalacce, 1 month ago
Jaehyun's Status Reports

Jaehyun’s Status Report for September 20, 2025

What did you personally accomplish this week on the project? Give files or photos that demonstrate your progress. Prove to the reader that you put sufficient effort into the project over the course of the week (12+ hours). I helped finalize the budget for the project. I helped research how Read more…

By jaehyun3, 1 month1 month ago
Recent Posts
  • Stella’s Status Report for October 11, 2025
  • Team’s Status Report for October 11, 2025
  • John’s Status Report of October 11, 2025
  • Jaehyun’s Status Report for October 11, 2025
  • Jaehyun’s Status Report for October 4, 2025
Recent Comments
    Archives
    • October 2025
    • September 2025
    Categories
    • Jaehyun's Status Reports
    • John's Status Reports
    • Stella's Status Reports
    • Team Status Reports
    Meta
    • Log in
    • Entries RSS
    • Comments RSS
    • WordPress.org
    • Design Review
    • Final Project Documents
    • Introduction and Project Summary
    • Proposal
    • Weekly Status Reports
    Hestia | Developed by ThemeIsle