Week of 10/13

This week our group made more progress in finishing our Minimum Viable Product. However, we had one team member out of town and another was sick, so we weren’t able to meet as often as we would have liked. However, we are still on track to finish the project on time given our slack. We are weary of last minute bugs that may crop up as we finish our code and it becomes complicated. Another aspect we have given plenty of time in case a problem does arise, is combining application features. We can definitely see a lot of issues during this last phase of putting everything together, so we are keen on testing individual units and making sure they work very well first.